HOME   WISE Uranium Project   >   Calculators   >

Uranium Mine Feasibility Calculator

(last updated Apr. 15, 2014)
Requires Netscape 3.0, Internet Explorer 3.0 or higher. JavaScript must be enabled.
For educational purposes only. No warranty.

Calculate the economic feasibility of a uranium mine and mill.   HELP new window

  1. Select a predefined parameter set, or enter and/or change parameters at your discretion,
  2. enter a value into any one field of the Lifetime Material Balance (if none was preset), and
  3. click the "Calculate" button.

"t" = metric tonne, "Mt" = million t, "Mlbs" = million lbs, "M$" = $ million, $ = US$.

Your browser does not support JavaScript, or you have disabled it.
The Calculator won't work.
Enable JavaScript (Preferences Menu) and reload the page.

 

Lifetime Material Balance
 Waste generatedReserve/Product
AmountAmountUranium contentsValue
[Mlbs U3O8][t U3O8][t U][M$]
Ore deposit  Mt Ore in situ
Mine Mt Waste Rock Mt Ore mined
Ore Sorting Mt Ore Reject Mt Ore post sorting
Mill Mt Mill Tailings t Ore Concentrate

Lifetime Cost Summary
Lifetime of operation: years
 Capital
Cost
Nominal
Oper. Cost
Subtotal
(Nominal Cost)
Long-Term
Mgmt. Cost
Total
(True Cost)
Mining M$ M$ M$ M$ M$
Ore Sorting M$ M$ M$ M$ M$
Milling M$ M$ M$ M$ M$
Gen. & Admin. M$ M$ M$ M$ M$
All stages M$ M$ M$
(=$/lb U3O8)
M$ M$
(=$/lb U3O8)
 
 Profit
at Nominal Cost
 Profit
at True Cost
(Ore Concentrate Value ./. Cost)M$
(=%)
 M$
(=%)


Specific Results

Resulting Specific Operating Cost   [$/lb U3O8 in Ore Concentrate]
 Nominal OperatingLong-Term Management
Mining $/lb U3O8 $/lb U3O8
Ore Sorting $/lb U3O8 $/lb U3O8
Milling $/lb U3O8 $/lb U3O8
Gen. & Admin. $/lb U3O8 $/lb U3O8
Total $/lb U3O8 $/lb U3O8

Resulting Uranium Concentrations
 in Waste generatedin Reserve/Product
Ore deposit Uranium Ore in situ: wt_% U
MineWaste Rock: (conc. not specified)Uranium Ore mined: wt_% U
Ore SortingOre sorting reject: wt_% UUranium Ore post sorting: wt_% U
MillMill Tailings: wt_% UUranium Ore Concentrate: wt_% U

Resulting Mass Flow
Mine Actual Mine Ore production rate: Mt/a
Actual Mine capacity usage: %
Ore Sorting Percentage of uranium contents in mined ore rejected by sorting: wt_%
Mill Actual Mill Ore processing rate: Mt/a
Actual Mill capacity usage: %
Actual production rate of uranium in ore concentrate:
  Mlbs/a U3O8   =   t/a U3O8   =   t/a U
General Overall uranium recovery from Ore in situ to Ore concentrate: wt_%


Parameter Entry


Select Parameter Set:
      
 

    Process Parameters    
Mine Grade of In Situ Ore: wt_% U   =   wt_% U3O8 (optional)
Waste/Ore Ratio:
Ore Production Capacity: Mt/a (optional)
Ore Extraction Losses: wt_%
Grade of Ore mined: wt_% U   =   wt_% U3O8
Ore Sorting Ore rejected: wt_%
Relative Ore grade improvement by sorting: %
Mill Ore Processing Capacity: Mt/a
Design Life: years (optional)
Extraction Losses: wt_% (auto estimate)
Uranium concentration in Ore Concentrate: wt_% U

    Cost Parameters    
 Capital CostNominal Operating CostLong-Term Management Cost
Mining $ per t/a mined
$ million
$ per t ore mined
$ per t waste rock
$ per t ore mined
$ per t waste rock
Ore Sorting $ per t/a mined
$ million
$ per t ore mined
$ per t ore reject
$ per t ore mined
$ per t ore reject
Milling $ per t/a milled
$ million
$ per t ore milled
$ per lb U3O8 produced
$ per t tailings
$ per t ore milled
$ per lb U3O8 produced
$ per t tailings
General and
Administrative
$ per t/a mined
$ million
$ per t ore mined
$ per lb U3O8 produced
$ per t ore mined
$ per lb U3O8 produced

    Price Parameters    
 Market Price
Natural Uranium in
Ore Concentrate

$ per lb U3O8   =   $ per kg U


> See also:

 

HOME   WISE Uranium Project   >   Calculators   >